Glencore’s Ulan Mine Modification 6

APPROVED, BUT CORE OBJECTIONS REMAIN UNADDRESSED

September 2026: Modification 6 has been approved by the NSW Department of Planning, Housing and Infrastructure. This is the 14th coal expansion approved by the Minns government.

Despite a successful November 2025 Land and Environment Court challenge that overturned the original approval, the Department has re-approved the amended proposal. The Department acknowledges the modification will "contribute to climate change impacts in the locality" — explicitly referencing the 2022 Wollar Valley floods and 2019-2020 bushfires — but concludes these impacts are "acceptable."

This approval comes despite MDEG and 74 community submissions calling for Mod 6 and Mod 8 to be assessed together as a new project, and despite critical objections to inadequate assessment of cumulative climate, water, biodiversity and cultural heritage impacts remaining substantively unaddressed.

The Core Problem: Cumulative Impacts Still Not Assessed

Why the Modification Pathway is Inadequate

The adequacy of climate impact assessment is precisely what MDEG successfully challenged in the LEC in November 2025. Using the same modification pathway for the resubmission, with incremental improvements rather than a fresh assessment, does not resolve that inadequacy.

MDEG's analysis of Glencore's Amendment 2 Response to Submissions finds that while some improvements have been made — Mod 8 is now acknowledged for the first time, and updated GHG targets included — the mine's responses to key objections remain procedurally compliant but substantively evasive. The 45% cumulative emissions increase from Mod 6 and Mod 8 combined is never engaged with. Glencore cannot argue against cumulative assessment of environmental impacts while simultaneously aggregating the entire UCC operation to justify its economic case.

Mod 6 alone — a two-year extension employing an unchanged workforce — contributes negligibly compared to the jobs the Central West Orana Renewable Energy Zone (CWO REZ) urgently needs.

Detailed Analysis: Why the Approval is Inadequate

The Amended Mine Plan: Only Surface Changes

The amended Mod 6 application has finalised the mine plan and now identifies the exact location of surface infrastructure and vegetation clearing. However, this highlights a key failure of the earlier approval, which included nine different infrastructure layout options, demonstrating that no final mine plan existed at the time it was approved and later overturned by the Court.

While the mine plan has now been refined, the approved proposal remains fundamentally flawed.

Subsidence from underground mining, combined with clearing for roads, pipelines, bores and ventilation shafts, will cause permanent damage to the landscape. The amended proposal focuses narrowly on updating select information and fails to reconsider the broader environmental consequences of extending mining in this region.

Critically, the proposal does not acknowledge that Mod 8 cannot proceed without Mod 6. By treating them as separate, small modifications, Glencore avoids the proper scrutiny of a new project application. This allows cumulative impacts to be overlooked and removes community merit appeal rights in the Land and Environment Court.

Greenhouse Gas Emissions: Scope 3 Still Ignored

Glencore does not publicly report methane emissions from Ulan Mine and maintains that the operation is a low emitter, asserting there are no feasible measures to reduce fugitive methane emissions.

The amended RtS shows only marginal improvement. For the first time, Glencore has provided specific Scope 1 and 2 emissions reduction targets (FY2030: 0.084 Mt CO₂-e; FY2035: 0.012 Mt CO₂-e) and references a NARCLiM-based climate impact assessment using NSW Government regional climate projections. However, these improvements do not resolve the fundamental failure: Scope 3 emissions — the combustion of exported coal, representing 99.4% of the project's total climate footprint — are still not adequately assessed in terms of their local environmental, social and economic impacts.

This assessment does not meet the requirements of the NSW Environmental Planning and Assessment Act. It fails to properly assess the environmental, social and economic impacts of all greenhouse gas emissions, including Scope 3 emissions, as required by law following the Mt Pleasant Mine decision. The NSW Net Zero Commission's Coal Mining Emissions Spotlight Report (December 2025) directly addresses this issue; the mine's response is to dismiss it as singling out coal unfairly.

Without full disclosure and assessment of emissions, the climate impacts of this project cannot be properly understood or justified.

Biodiversity: Cumulative Habitat Loss Not Assessed

The approved Mod 6 proposal will directly impact threatened species habitat, including:

  • Large-eared Pied Bat
  • Eastern Cave Bat
  • Powerful Owl
  • Barking Owl
  • Southern Myotis

The Large-eared Pied Bat and Eastern Cave Bat use sandstone escarpment for breeding and roosting. Subsidence from underground mining poses a direct risk of rockfall and cave collapse in this habitat. The amended RtS now names these species and undertakes a Serious and Irreversible Impact (SAII) assessment — concluding none face SAII from Mod 6 alone. However, this assessment is conducted in isolation. The combined subsidence footprint across Mod 6 and Mod 8 on the same sandstone escarpment system has never been assessed.

These species are already experiencing cumulative habitat loss across multiple coal mines in the Mudgee region, including the proposed Moolarben Open Cut 3 extension. These cumulative impacts have not been assessed as SAII across all three mines.

The proposal also fails to assess the cumulative loss of Box Gum Woodland, a critically endangered ecological community, across the region as an SAII entity.

Water Impacts: Permanent Groundwater Damage

Underground mining causes subsidence and land collapse that permanently damages groundwater systems. These systems store water in the landscape and provide base flows to rivers and creeks.

When combined with Mod 8, this expansion will result in a significant additional loss of flow to the Talbragar River. Allowing this modification to be approved separately from Mod 8 does not allow for cumulative water loss assessment.

The Talbragar River is a major tributary of the Macquarie River in the Murray–Darling Basin and flows downstream of Burrendong Dam. These flows are directly connected to the internationally significant Macquarie Marshes — which were listed as an Endangered Ecological Community under the EPBC Act in January 2026, a material change in environmental context that demands fresh assessment of cumulative downstream water impacts.

The Federal Independent Expert Science Committee (IESC) has previously made significant comments:

"Modelled predictions of water interception from Ulan Mine have consistently underestimated impacted volumes. The Independent Expert Scientific Committee has limited confidence in the groundwater model used to predict impacts from this mine on surface and groundwater."

Original Independent Expert Advisory Panel on Mining (IEAPM) report findings:

  1. Additional monitoring bores required to measure groundwater interception
  2. Inadequate trigger levels for impacts on groundwater systems
  3. Inadequate monitoring of impacts on private bores
  4. The groundwater model is inadequate for predicting long-term impacts
  5. Significant risk of drawdown beneath Mona Creek in all underlying groundwater systems
  6. A formal peer review of the groundwater model is required

Glencore's response to the IEAPM findings is totally inadequate, proposing that any additional monitoring should occur after mining has commenced. Monitoring damage after the fact is not a sustainable way to protect water sources and the environment.

Key issues with Glencore response to IEAPM:

  • The groundwater model does not capture delayed drawdown responses post mining — when they are most likely to happen
  • Impacts on private bores post mining is not modelled
  • Additional reporting is required for each type of impacted water source
  • Long term impacts on groundwater over time are not being measured
  • Additional mapping is required to identify Groundwater Dependent Ecosystems relying on shallow groundwater

It is essential that a Water Management Plan, including Surface Water Management and Groundwater Management, that covers Mod 6 + Mod 8 impacts be completed before a determination can be made on this expansion of the Ulan Mine.

The current process for approving large underground mining operations allows for groundwater models to be 'recalibrated' or adjusted if drawdown parameters have been exceeded or varied. This approach does not adequately assess the long-term impacts on the groundwater system over time.

Aboriginal Cultural Heritage: Cumulative Impacts Unassessed

The proposal does not adequately assess the cumulative loss of Aboriginal cultural heritage in the Ulan area. There is extensive evidence of continuous Wiradjuri occupation and enduring spiritual connection to Country. The amended RtS provides a more detailed heritage response than the original, acknowledging Wiradjuri spiritual connection and noting agreement from Wellington Valley Wiradjuri Aboriginal Corporation elders. However, agreement from one Registered Aboriginal Party does not constitute comprehensive cumulative heritage assessment across the region.

A significant number of cultural heritage values will be impacted by Mod 6, with far greater losses occurring when combined with Mod 8. These cumulative impacts have not been properly identified or assessed.

Regional Jobs and Economic Justification: No Demonstrated Need

There is no demonstrated need to extend coal mining in the region to support local jobs. Glencore's economic justification aggregates employment and regional benefit across the entire UCC operation — but Mod 6 alone is a two-year extension employing an unchanged workforce. Assessed on its own terms, as Glencore insists environmental impacts must be, its employment contribution is negligible.

Coal mining is competing for skilled labour urgently needed in construction, housing and renewable energy. The Central West is experiencing a major labour shortage as workers are required for the development of the Central West Orana Renewable Energy Zone. Glencore's own RtS attempts to counter this by citing research arguing that renewable energy jobs are short-term and construction-focused — but this ignores the long-term operational workforce the CWO REZ requires, and fails to quantify whether a two-year coal extension outweighs the opportunity cost to the renewable transition.

The NSW Government has established the Central West Future Jobs and Investment Authority to support the transition away from coal. The Mudgee region has strong opportunities to diversify its economy, but further coal expansion will slow this transition and lock in long-term environmental damage.

In Conclusion: The Approval Does Not Resolve Fundamental Inadequacies

The amended Mod 6 proposal has been approved, but the core objections remain unaddressed. While the mine now acknowledges Mod 8 and has improved its GHG assessment, the fundamental failures persist.

The mine's responses are procedurally compliant but substantively evasive. The decision to approve Mod 6 on the modification pathway rather than as a new project continues to deny the community the full scrutiny, appeal rights and independent oversight this expansion warrants.

Mod 6 and Mod 8 remain interdependent and should have been assessed together as a single 'new project', not two separate 'modifications', to fully understand their cumulative impacts on climate, water, biodiversity and cultural heritage.

MDEG will continue to advocate for proper cumulative assessment as these applications progress. Further expansion of the Ulan Coal Mine is incompatible with a safe climate, healthy water systems, and a just transition for the Central West.

Key Points of Objection

  1. Cumulative assessment required: Mod 6 and Mod 8 must be assessed together as a new project to provide robust cumulative impact information.
  2. Climate impact assessment: The approval still fails to fully identify the impacts of the increased greenhouse gas emissions on the local environment, community and economy, as required under NSW planning law.
  3. Emissions scale: The proposal will produce an additional 18.8 million tonnes of coal and when combined with Mod 8 (additional 43 MT) there will be over a 45% increase in total emissions above current approved operations at Ulan Mine.
  4. Regional mine cumulative impacts: There is no assessment of cumulative impacts from existing mine approvals or expansion proposals across the three Mudgee Mines: Ulan, Moolarben, Wilpinjong.
  5. Habitat and heritage loss: The cumulative loss of threatened species habitat, significant Aboriginal cultural heritage values, water from the landscape and flows to creeks and rivers, and threats to amenity and livelihoods of neighbours has not been assessed.
  6. Workforce competition: The proposal is within the CWOREZ and is competing for regional workforce urgently needed for new industries in the Central West.
  7. Water stress: The proposal will place further pressure on already stressed surface and ground water sources within the Murray Darling Basin.

Key Links and Resources

Court and Government Documents:

Expert and Government Advice:

MDEG Resources:

Related Expansions:

What Happened (a timeline):

May 2025
The NSW Department of Planning approved Glencore’s Ulan Coal Mine Modification 6 (Mod 6), despite the mine plan being incomplete and key environmental impacts unresolved. The approval relied on flexible conditions and allowed major decisions about mine layout, infrastructure and biodiversity impacts to be deferred until after approval.

November 2025
The approval was overturned by the NSW Land and Environment Court. By consent, the Court declared the Mod 6 approval invalid and set it aside. The ruling followed recent court decisions confirming that climate impacts must be properly assessed for all fossil fuel projects, including mine modifications.

December 2025 – January 2026
Glencore immediately re-applied for Mod 6 approval, placing an amended proposal on public exhibition over the Christmas holiday period. The revised application presents a single “final mine plan” and claims greenhouse gas emissions are not significant.

November 2025 (separately)
Glencore also placed Modification 8 (Mod 8) on public exhibition. Mod 8 proposes a much larger expansion, extending mining until 2041 and disturbing extensive new areas of bushland and farmland. Mod 8 cannot proceed without Mod 6.

December 2025 – January 2026 Glencore immediately re-applied for Mod 6 approval, placing an amended proposal on public exhibition over the Christmas holiday period. Rather than lodge a new project application — which would require full independent scrutiny and restore community merit appeal rights — Glencore resubmitted on the same modification pathway, reverting to the original 2008 approval as its baseline and effectively leapfrogging the LEC ruling.

15 January 2026 The Macquarie Marshes were listed as an Endangered Ecological Community under the EPBC Act — a material change in environmental context that demands fresh assessment of cumulative downstream water impacts from Ulan, Moolarben and Wilpinjong mines combined. The listing post-dates the amended proposal and has not been properly assessed.

Early 2026 The community objection period closed. 74 submissions raised the interaction between Mod 6 and Mod 8, calling for joint assessment as a new project — the single most common theme across all submissions.

March 2026 Glencore released its Amendment 2 Response to Submissions (RtS). While marginal improvements were made — Mod 8 is now acknowledged for the first time, and updated GHG targets included — MDEG's analysis finds the responses to key objections remain procedurally compliant but substantively evasive.

September 2026 Modification 6 was approved by the NSW Department of Planning, Housing and Infrastructure. The Department's supplementary assessment report acknowledges that the modification will "contribute to climate change impacts in the locality" but concludes these impacts are "acceptable when weighed together with all relevant mandatory considerations."

Take Action Now

Local Mines

Socials